GCFD seal

 Glynn County Fire Department - Protectors of Life and Property Since 1952

 
   

 

Demere Rd. Fire Station construction on target

By: Matthew J. Permar / The Islander

July 4, 2005

 

The management team overseeing the construction of Glynn County Fire Station #2 on St. Simons Island met on-site last Thursday morning to review the project status. The group includes: (left to right) Fire Chief Al Thomas; county SPLOST construction consultant Marshall Davis of Carter Goble & Lee; Fire Inspector Capt. Jerome Johnson; project manager John Moore of the Hussey, Gay, Bell & DeYoung, International architectural firm in Savannah; construction manager Chris Chesser of McKnight Construction in Augusta, Ga. and Travis Thomas, Carter Goble & Lee resident engineering inspector.                     (Islander Staff Photo)

Mid-September is expected completion date for Fire Station #2 on St. Simons

Even with the seasonal summer rain that graced St. Simons Island week, construction on Glynn County Fire Station #2 at the intersection of Demere Rd. and Airport Rd. progressed without delay.

According to everyone connected with project management, the fire station is well under way and on target to be completed by the contract completion date in mid-September.

Last week, on Thursday, June 30 project management met and reviewed the construction status. The group included Glynn County Fire Chief Al Thomas; Fire Inspector Capt. Jerome Johnson; county Special Purpose Local Option Sales Tax construction consultant Marshall Davis of Carter Goble & Lee; project manager John Moore of the Hussey, Gay, Bell & DeYoung, International architectural firm in Savannah who designed the building; construction manager Chris Chesser of McKnight Construction in Augusta, Ga. and Travis Thomas, Carter Goble & Lee resident engineering inspector.

Chesser told the group the parking lot was finished and draining well.

“All that is left with the grounds,” said Chesser, “is the final grade, bringing in a little top soil and cleaning up the debris. After that we’ll turn it over to the landscaper and let him loose with the sod. I want to get that down quick to keep erosion down.”

As far as the building itself, Chesser said, “All the tile in the bathrooms is done. Mastercraft did a good job there.”

Continuing, Chesser said the large overhead doors for the four-bay station are in Brunswick ready to be installed by Overhead Door Co. Chesser said as soon as the sheet rock in the fire truck bay is done and the ceiling hung, the overhead doors would be installed so they can close that part of the building off and keep the moisture out before putting the floor down.

Chesser said they would be testing the sprinkler system, and setting the HV/AC and generator soon. The case work is set for the week of July 11.

During the meeting last week, Marshall Davis told The Islander, “This is the same construction company that did the public health center on Fourth Ave. Since they started here the project has either been ahead of schedule or on target. I see no problems with finishing on time. Even the rain this week has not been a problem.”

The construction portion of the SPLOST 4 project is $1.75 million.

The west end will house the fire department, while the east end will contain the island police precinct, a satellite county commissioner’s office and a public conference facility that will hold 50 to 60 people.

The 900 sq. ft. conference room’s audio visual equipment is being upgraded to allow for taping of the St. Simons Island Planning Commission meetings.

Chief Thomas said the plan is to re-locate the equipment and apparatus from the existing Station #2 on Demere Rd. near Arnold Rd. to the new station. The apparatus includes the ER squad truck, a fire engine and a mini-pumper. Being a four-bay station, the chief said future plans include an aerial truck for the island.

Davis concluded, “The job has gone well and personally I’m proud of this one. With the design, shape, materials and color, it doesn’t look like a standard, government, industrial building.”

 

 

As published in "The Islander", July 4, 2005, Vol. 33 Issue 27

 

GCFD seal

 

Fire & Rescue Emergency

Dial 911

 Copyright © 2002-2010, ALL RIGHTS RESERVED

 

 

Site Map | Headlines | What's New?

Terms of Use | Submission Guidelines | HIPAA Patient Privacy

Contact Us